Annex A CLG Restructure Update Feb 2021

Activity

Dates

Consultation

Share proposals with CMT, CLG, Heads of Service, Trade Unions and Executive.

w/c 9 November

Share Proposals with wide elected members – Group Leaders, request feedback by 27 November

w/c 9 November

Arrange feedback sessions for CLG with COO

-       Group session

-       Individual sessions by request

Between 16 – 27 November

Attend group meetings to discuss proposals – if requested

By 27 November

Consider all feedback and amend proposals where applicable to be considered by SMU

By 3 December 2020

SMU Paper Published including draft job descriptions

4 December 2020

SMU paper shared with all CLG, Trade Unions and all 47 elected members

4 December 2020

SMU Committee

14 December 2020

CLG Updated following discussion at SMU

15 December 2020

Formal consultation Phase

First formal consultation meeting (30 day consultation period) with staff and the trade unions. Share the written proposal report, draft JD’s and timeline. Share current JD’s with all staff.

In scope letter issued following consultation meeting.

15 December 2020

 

15 December 2020

Group & individual consultation sessions through workshops / team meetings / 1:1’s etc. All staff will be invited to attend an individual 1:1 meeting.

At 1:1 meetings, staff will be asked to confirm that their job description is the latest version.

15 December 2020  - 22 January 2021

 

 

End of consultation period & deadline for final feedback on the proposed structure and all JD’s by staff and Trade Unions.

22 January 2021

 

New job descriptions go through Job Evaluation Process to confirm grades.  

Wc 25 January 2021

Share final proposal with SMU for sign off.  

Paper published 29 January for SMU on 1 February 2021

Meeting with staff and TUs to confirm the feedback considered, any amendments to the original proposal and to share the final structure and job description grades.

28 January 2021

Meet again if significant change  at SMU on 1 Feb 2021

IMPLEMENTATION PHASE

Assimilation panel held and outcome letters issued to staff. 

4 February 2021

Staff identified at this stage as potentially ‘at risk’ provided with Redeployment Profile Form to complete and offered 1:1 meetings with manager.

Allow 2 weeks for staff to complete. Staff placed on the redeployment register.

5 February 2021

 

19 February 2021

Deadline for assimilation appeals (appeals received within 10 working days of the date of notification letter).

19 February 2021

Assimilation appeals.

Appeals to be heard 25 February 2021

Outcomes of the Appeals process notified to staff

25 February 2021

If necessary, competitive interviews take place – dependant upon the assimilation panel meeting outcome & any subsequent appeals.

Interviews week of 1Interviews week of 1 March 2021

Outcome letters (following interviews if take place) and/or invite to redundancy hearing letters issued to staff & 1:1 meetings to review and confirm next steps.

W/c 8/3/2021

Skills matching exercise (if necessary) to any remaining posts in structure, if applicable (for staff identified ‘at risk’ and placed on redeployment register - having completed Redeployment Profile Form).

Individuals notified of outcome of skills matching process.

 

Redundancy hearings for staff identified as redundant due to either their post being deleted or not assimilated in to the new structure.

Contractual notice is issued (dependant on timescales some individual’s contractual notice may go beyond structure implementation date).

 

 

Implementation date of the new structure.

1 April 2021

THESE DATES ARE SUBJECT TO CHANGE DEPENDING ON THE

OUTCOME OF THE CONSULTATION PROCESS.